| Fort Bend Technical Center | |||||||||
| Item | Amenities | Life Safety | Gen. Maint. | Deficiency | Regulations | Last Sched. | Next Sched. | Est. Cost | ACTUAL COST |
| Exterior | |||||||||
| ADA Ramp | Repaint Ramps $300 | 2006 | $300 | ||||||
| Roofs | |||||||||
| Brick/washed & | $14,865 29,730 sq.ft. .50 sq.ft. | 2001 | 2011 | $14,865 | |||||
| sealed | |||||||||
| Interior | |||||||||
| Indoor air quality | $73,350 81,500sq.ft. .50sq. ft. | $73,350 | |||||||
| Alarms | |||||||||
| Horn strobes | |||||||||
| Sprinkler | |||||||||
| Smoke detector | |||||||||
| Floors | $26,423 15,854 sq.ft. carpet | $26,423 | |||||||
| Ceilings | 5 cases ceiling tiles $37 each | 2005 | $185 | ||||||
| Amenities | Life Safety | Gen. Maint. | Deficiency | Regulations | Last Sched. | Next Sched. | Est. Cost | ACTUAL COST | |
| Furn. Fixt. & | $10,000 | $10,000 | |||||||
| Equip | |||||||||
| ADA Restrooms | |||||||||
| ADA Hardware | |||||||||
| ADA Signage | |||||||||
| Other | |||||||||
| Electrical | $16,666 | $16,666 | |||||||
| HVAC | $16,666 | Coating of chillers 5000 each | 2007 | $16,666 | $10,000 | ||||
| Plumbing | $16,666 | $16,666 | |||||||
| Paint | $16,666 | $16,666 | |||||||
| Carpentry | $16,666 | $16,666 | |||||||
| TOTAL ALL | $10,000 | $183,103 | $14,865 | $207,968 | $10,485 | ||||
| Variance | |||||||||